This page gives an overview of the pathway build.
For the latest build news, please see our Construction updates page.
Build timeline
Here’s an overview of the technical, design and construction work already completed.

A project overview timeline and a consultation timeline are also available.
Future dates
Here are our best estimates for the work coming up.
2021
- Technical work underway on preliminary and detailed design for Areas One and Two
- Two out of three Rizal Reserve sections scheduled for completion
- Public consultation will run from 22 November to 20 December
2022
- Construction estimated to start
- Detailed design will continue
2024
- Construction on Areas One and Two due to be completed